GIYC Project Update July 2010
All Praise is due to Allah
Alhamdulilah, we are progressing extremely well in the fit out stage of the Casula premise. The electricity and plumbing is almost all completed. The bathroom walls and amenities as well as the kitchen are under construction. We have also completed the selection of the carpet. There is still plenty to do such as air conditioning, tiling, ceiling etc. We are working very hard to have the centre ready as soon as practically possible. However we do not anticipate that we will be ready to use it during the coming Ramadaan. Hence we request you to please be patient with us and come and enjoy one last Ramadaan with us in Liverpool.